What is a ci casting foundry by induction furnace project report?
A CI casting foundry by induction furnace project report is a detailed project report (DPR) for a unit that melts pig iron and scrap in an electric induction furnace and pours grey iron castings into sand moulds. It sets out the process, machinery, charge mix, power load, project cost, finance, five-year projections, DSCR and break-even.
Promoters use it to size the furnace and moulding line and to raise a term loan; banks use it to judge whether casting margins can carry the debt.
Also known as: cast iron foundry, grey iron foundry.
CI casting foundry plant cost in India: the sample economics
The sample report models a grey iron foundry making 8.6 metric tonnes per day (MT per day) of good castings. Working 330 days, it can turn out 2,838 MT a year at full capacity. It starts at 60% utilisation and reaches 80% in Year 5, selling at ₹1,04,000 per MT.
| Land and site development | 96.42 |
|---|---|
| Building and civil works | 221.05 |
| Plant and machinery | 460.23 |
| Other fixed assets | 42.16 |
| Contingencies | 34.06 |
| Preliminary and pre-operative | 21.35 |
| Working capital margin | 73.32 |
| Total | 948.59 |
| Promoter's contribution (25%) | 237.15 |
|---|---|
| Term loan from bank (75%) | 711.44 |
| Cash credit limit (separate) | 219.96 |
| Total project cost | 948.59 |
Term loan at 10.5% with a 6-month moratorium and 54 monthly instalments; lowest yearly DSCR 1.33. All figures are illustrative.
CI casting foundry manufacturing process, step by step
A jobbing grey iron foundry works to the buyer's drawing, so every new part starts with a pattern and an approved sample. Production then runs through eight stages.
- Pattern and core making
Wood, metal or resin patterns are made from the drawing, and resin-bonded sand cores are shot and cured to form internal passages such as pump volutes.
- Sand preparation
Return sand is cooled, screened and mixed in a muller with fresh silica sand, bentonite and water; moisture and compactability are tested every shift.
- Moulding
Jolt squeeze machines ram green sand around the pattern in two flask halves, cores are set, and the mould is closed and clamped.
- Melting
Pig iron, foundry returns, steel scrap and ferro alloys are charged into the induction furnace and melted to about 1,450–1,500 degrees Celsius.
- Testing and pouring
A spectrometer checks carbon, silicon and other elements, the metal is inoculated in the ladle, and moulds are poured within a few minutes to avoid fade.
- Knockout
After cooling, moulds are broken on a shakeout grid; castings go to fettling and the sand returns to the sand plant.
- Fettling and finishing
Runners and risers are cut off and remelted, castings are shot blasted, and fins and parting lines are ground smooth.
- Inspection and dispatch
Hardness, dimensions and surface defects are checked against the buyer's specification, then castings are primed if required and dispatched.
Induction furnace or cupola for melting cast iron?
Grey iron can be melted in a coke-fired cupola or an electric induction furnace. Most new jobbing foundries choose induction because it suits small batches of many grades, but the trade-offs belong in the report.
| Energy source | Induction runs on electricity, so the power tariff and sanctioned load decide melting cost. A cupola burns foundry coke. |
|---|---|
| Chemistry control | Induction gives close control of carbon, silicon and temperature, which helps with higher grades such as FG 260 and above. Cupola chemistry varies more with coke and blast. |
| Operating pattern | An induction furnace melts in batches and can be started and stopped to suit orders. A cupola is most economical on long continuous runs of one grade. |
| Emissions | Induction avoids coke combustion gases, though fume extraction is still needed at charging and tapping. A cupola needs a wet scrubber or bag filter for flue gas. |
| Furnace sizing | Small foundries often run two crucibles on one power supply, so one melts while the other pours. Furnace kW and crucible size are set from the daily tonnage and pouring rate. |
Raw materials for CI castings: pig iron, scrap and alloys
The charge is a mix of foundry grade pig iron, your own returns and bought scrap, adjusted with ferro silicon and ferro manganese to hit the grade. In our sample, metallic charge (pig iron plus scrap) is 70% of raw material cost, and raw materials are 63.8% of sales.
| Raw material | Share of cost | Year 3 (₹ lakh) |
|---|---|---|
| CI and steel scrap | 36% | 474.70 |
| Foundry grade pig iron | 34% | 448.33 |
| Ferro alloys and inoculant | 9% | 118.68 |
| Silica sand and bentonite | 9% | 118.67 |
| Core sand and resin binders | 6% | 79.12 |
| Furnace lining ramming mass | 6% | 79.12 |
| Total | 100% | 1,318.62 |
Shares are the sample report's assumptions. Pig iron and scrap prices move every month, so get current rates before you finalise.
Machinery for an induction furnace foundry
The melting furnace is the single largest item, at ₹165.68 lakh of the ₹460.23 lakh machinery cost in our sample. The sand plant and moulding machines come next, because they decide how many good moulds the shop makes per shift.
| Machine | What it does | Sample cost (₹ lakh) |
|---|---|---|
| Medium frequency induction furnace with power panel | Melts the charge; includes crucibles, panel and cooling | 165.68 |
| Sand plant with muller and sand cooler | Reconditions and mixes green sand | 69.03 |
| Jolt squeeze moulding machines | Ram the moulds around the pattern | 55.23 |
| EOT crane and pouring ladles | Carry liquid metal from furnace to moulds | 41.42 |
| Shot blasting machine | Cleans sand and scale off castings | 32.22 |
| Spectrometer and sand testing lab | Checks melt chemistry and sand properties | 32.22 |
| Core shooter and core oven | Makes and cures sand cores | 23.01 |
| Fettling and grinding equipment | Removes runners, risers and fins | 23.01 |
| Fume extraction and dust collector | Captures fume at the furnace and dust at knockout | 18.41 |
| Total plant and machinery | 460.23 | |
Costs are the sample report's estimates for an 8.6 MT per day foundry. Get current quotations before you finalise.
Manpower and power for a grey iron foundry
A foundry is labour heavy at moulding, knockout and fettling. Our sample plans 54 people in Year 1, and takes power and fuel at 6.9% of sales, or ₹142.85 lakh in Year 3.
| Role | People | Monthly wage (₹) | Annual cost (₹ lakh) |
|---|---|---|---|
| Management, supervision and administration | 8 | 30,500 | 29.28 |
| Skilled workers and operators | 19 | 19,500 | 44.46 |
| Semi-skilled and unskilled workers | 27 | 13,000 | 42.12 |
| Total | 54 | 115.86 |
Check power per tonne, not just the load: a study published by the Institute of Indian Foundrymen cites a CII norm of 620 kWh per tonne of liquid iron for induction melting. The foundries it studied used 700–750 kWh. Every remelted riser and rejected casting adds to this, so yield and rejection rate belong in the power estimate.
Licences, pollution category and BIS rules for a CI foundry
Grey iron castings now sit under a Quality Control Order, so the BIS position needs settling before machinery is ordered. The other approvals follow the usual factory route, with a few foundry-specific points.
| BIS certification | IS 210:2009 (grey iron castings) is listed in the Cast Iron Products (Quality Control) Order, 2024, S.O. 2287(E) of 13 June 2024. IS 1726 applies if you make manhole covers and frames. |
|---|---|
| QCO exemptions | Udyam units with plant and machinery up to ₹25 lakh at original cost and previous-year turnover up to ₹2 crore are excluded, as are goods made only for export. A unit the size of our sample is above this limit. |
| Pollution board consent | Consent to establish and operate from the State Pollution Control Board. Foundry operations below 5 tonnes per hour and under 500 kg per hour of coal use are listed in the Orange category under CPCB criteria. |
| Power connection | An HT connection sanctioned for the furnace load plus auxiliaries, with a dedicated furnace transformer; the furnace kW rating drives the sanction. |
| Registrations | Udyam and GST registration, factory licence under the Factories Act, and fire NOC where the state requires it |
Rules and categories vary by state and change over time. Confirm with BIS and your State Pollution Control Board before applying.
Who buys grey iron castings from a jobbing foundry
Grey iron is cast to order. Engineering companies outsource bodies, housings and machine parts to nearby foundries that can hold the grade and deliver on schedule. That is why foundries group into clusters close to pump, motor, tractor and machine tool makers.
Established clusters such as Coimbatore, Belgaum and Ahmedabad grew around exactly these buyers: pumps and wet grinders, tractor and machine tool parts, and textile machinery spares.
- Pump, valve and compressor manufacturers
- Automobile and tractor component suppliers
- Electric motor and gearbox makers
- Machine tool and textile machinery builders
- Municipal and infrastructure contractors for manhole covers and gratings
Where a new foundry wins: buyers move work only after a sample is approved, so the first months go on trials. A report that plans for a slow ramp-up and a raw material price clause in buyer contracts is more credible to a bank.
Mistakes that weaken a CI casting foundry by induction furnace project report
- Treating liquid metal as saleable output
Runners, risers and rejects are remelted, so tonnes of good castings are well below tonnes melted. Sales and power per tonne must use realistic casting yield.
- Sizing the furnace without the pouring line
A large furnace adds nothing if the moulding line cannot take the metal. Furnace kW, crucible size and moulds per hour must match.
- Leaving out lining and refractory cost
The crucible is relined regularly with ramming mass. Missing it under-states running cost and downtime.
- No plan for the BIS licence
With IS 210 under a Quality Control Order, a report with no budget or time for certification leaves a gap lenders will ask about.
- Ignoring sample approval time
New buyers take weeks to approve patterns and samples. Assuming full orders from month one inflates Year 1 cash flow.
How NPCS helps you plan a CI casting foundry
- Furnace and line sizingMatch furnace rating, crucibles and moulding capacity to your target grades and daily tonnage.
- Charge mix and costingBuild the pig iron, scrap and alloy mix, casting yield and power per tonne into the cost sheet.
- Bank-ready project reportProjections, DSCR and working capital in the format your lender expects.
- Approvals and layoutFoundry layout, HT power load, pollution consent and the BIS position for your castings.
NPCS, led by founder Ajay Kumar Gupta, has prepared project reports and feasibility studies for steel, castings and metal product units since 1994. Its client list records 116 assignments in this sector.
What's inside the ci casting foundry by induction furnace sample report
- Introduction
- Uses and applications
- Market potential
- Manufacturing process
- Raw materials
- Plant and machinery
- Land, building and utilities
- Manpower
- Licences and approvals
- Project cost and means of finance
- Working capital
- Projected profitability
- Cash flow statement
- Projected balance sheet
- Depreciation
- Term loan repayment
- Debt service coverage
- Break-even analysis
- Financial ratios
- Key assumptions
- Conclusion
- Monthly loan repayment schedule
19 pages, five-year projections, illustrative figures.
Open sample reportFree sample or a report for your project?
| What you get | Free sample | NPCS report for your project |
|---|---|---|
| Capacity and location | Typical unit | Your capacity, site and state |
| Figures | Illustrative | Built on current prices and quotations |
| Machinery suppliers and quotations | No | Yes |
| Market survey for your region | No | Yes |
| Bank or scheme format (PMEGP, term loan) | No | Yes |
| Use for a loan application | No | Yes |
Find NPCS project reports in your budget
What clients say about NPCS
4.7
264 Google reviews, as of 20 Oct 2026
Clients most often mention
- feasibility reports 18
- project report 16
- helpful for startups 15
- detailed reports 8
-
Excellent experience with Niir Project Consultancy Services. Their Techno-Economic Feasibility Reports are incredibly detailed and backed by solid market data.
Piyush Singh, Google review, 2026
-
Niir Project Consultancy Services offers excellent guidance for business setup. Their market survey and feasibility reports saved us a lot of time and helped us make informed decisions. Highly recommended
Saroj Yadav, Google review, 2026 View on Google
-
In an era of information overload, NIIR stands out for its precision. Their technical consultancy and market feasibility studies are world-class.
Shrishti Gautam, Google review, 2026
-
NIIR Project Consultancy Services provides useful books and reports for students, entrepreneurs, and small businesses. Their content is easy to understand and focuses on practical ideas for starting and managing industries. Overall, NIIR is helpful for learning about business and project planning.
Raj Yadav, Google review, 2026
CI Casting Foundry by Induction Furnace project report: frequently asked questions
What is the cost of setting up a CI casting foundry with an induction furnace in India?
Our sample report models an 8.6 MT per day grey iron foundry at ₹949 lakh, including land, building, ₹460 lakh of plant and machinery and working capital margin. As an indicative guide, a 3–5 MT per day jobbing foundry with manual moulding can start at about ₹3–6 crore. Furnace size, moulding method and land cost move the figure most.
Which machines are needed for an induction furnace foundry?
The core items are a medium frequency induction furnace with its power panel and cooling system, a sand plant with muller and cooler, moulding machines, core shooters, an EOT crane with ladles, a shot blasting machine, fettling grinders, a spectrometer and a fume extraction system. In our sample the furnace and its power panel take about 36% of machinery cost.
How much power does an induction furnace use to melt cast iron?
A paper presented at the Indian Foundry Congress cites a CII norm of 620 kWh per tonne of liquid iron, while the foundries it studied used 700–750 kWh per tonne. Power per tonne of good castings is higher because runners, risers and rejects are remelted. Your report should use your furnace rating, yield and electricity tariff.
Is a CI casting foundry profitable?
In our illustrative sample, the 8.6 MT per day foundry earns a 16% return on investment in Year 3, breaks even at 43% of capacity and pays back in about 4.2 years, with an average DSCR of 1.52. Real results depend on pig iron and scrap prices, casting yield, rejection rate and how quickly buyers approve your samples.
Do grey iron castings need a BIS licence?
IS 210:2009 for grey iron castings is listed in the Cast Iron Products (Quality Control) Order, 2024, notified by DPIIT in June 2024. The order exempts Udyam units with plant and machinery up to ₹25 lakh and turnover up to ₹2 crore, and goods made only for export. Confirm with BIS whether your castings fall within its scope before production.
Induction furnace or cupola: which is better for a new foundry?
Most new grey iron foundries choose an induction furnace because it gives close control of chemistry and temperature, melts in batches to suit job orders and avoids coke handling. A cupola has lower running cost per tonne for long runs of one grade but needs more emission control. The choice depends on your power tariff and order pattern.
Is the sample report free and can I use it for a loan?
The sample is free to view and download. It is an illustrative report that shows the format and depth of an NPCS report; its figures are representative and not based on a real project, so it should not be submitted to a bank. For a loan, NPCS prepares a report for your own capacity, location and loan scheme.
Sources and references
- Cast Iron Products (Quality Control) Order, 2024 (S.O. 2287(E))Bureau of Indian Standards (DPIIT order), checked Oct 2026
- Categorisation of industrial sectors under Orange as per CPCB criteriaState Pollution Control Board, Odisha, checked Oct 2026
- Energy consumption studies in cast iron foundries (Transactions of 57th IFC, 2009)The Institute of Indian Foundrymen, checked Oct 2026
- Foundry sector and clustersBureau of Energy Efficiency (SIDHIEE), checked Oct 2026