RCCB and MCB: How They Differ and How They Are Made in India

rccb-mcb-manufacturing
Contents 10 sections
  1. RCCB and MCB side by side: what each one trips on
  2. Which comes first in the board, and do you need both?
  3. What do an RCCB and an MCB cost in India?
  4. Which standards and approvals apply to an RCCB and MCB plant?
  5. What goes into an MCB and an RCCB?
  6. How are MCBs and RCCBs made, step by step?
  7. Which machines and test equipment does the plant need?
  8. What does an MCB plant cost, per the NPCS project report?
  9. What should you do before committing to an RCCB and MCB plant?
  10. Frequently asked questions

RCCB and MCB sit side by side on a distribution board and do different jobs. An MCB (miniature circuit breaker) protects wiring and appliances from overload and short circuit. An RCCB (residual current circuit breaker) protects people, by tripping the moment current leaks to earth through a fault or a body. Neither can do the other's job, so a home board carries both, with an RCCB at the incoming side and an MCB on every outgoing circuit.

For a manufacturer, both are assembled products, not process plants. A factory buys housings, contacts, bimetal strips and coils, assembles each breaker, sets its trip point and tests every piece.

RCCB and MCB side by side: what each one trips on

The MCB senses how much current flows. The RCCB senses whether the same current comes back.

MCB

RCCB

Combined unit

Trips on

Overload, short circuit

Earth leakage (live and neutral out of balance)

Both

Protects

Wiring, appliances

People, and fire risk from leakage

Both, one circuit at a time

Cannot see

Earth leakage

Overload, short circuit

Neither

The combined unit is called an RCBO. An RCCB can never replace an MCB. Only an RCBO does both jobs in one casing.

Which comes first in the board, and do you need both?

You need both. BIS defines the RCCB as a breaker without its own overcurrent protection, so another device must guard the circuit behind it, and the MCB cannot detect leakage. BIS's note on RCBOs also cites Regulation 44 of the CEA safety regulations, 2023, which mandates a residual current device in installations. For a new connection the RCCB is not optional.

The usual order is main switch, RCCB, then one MCB per outgoing circuit. Some installers add a main MCB ahead of the RCCB. Either way, the RCCB's current rating must not be lower than the load behind it.

A 30 milliamp rating is the usual choice for homes; the Puducherry electricity department's self-certification annexure sets it as the ceiling for the RCD on the supply. One RCCB per board works for a flat. Give the refrigerator and air conditioner their own RCBOs so a leak elsewhere does not switch them off.

What do an RCCB and an MCB cost in India?

Price follows protection type, poles and brand more than current rating. ABB India's online shop shows the spread, prices including 18% GST.

Device (ABB India listing)

Price (₹)

MCB, 1P, 32 A, 10 kA, B curve

MRP 490; sellers about 160-190

RCCB, 2P, Type AC, 30 mA, 25 A

2,125

RCCB, 4P, Type A, 100 mA, 40 A

6,860

RCCB, 2P, Type B, 30 mA, 25 A

54,880

Type B suits sensitive electronic loads such as EV chargers and solar, and costs roughly 26 times a Type AC of the same size (₹54,880 against ₹2,125). Figures are from ABB India's RCCB listing and its SB200M MCB page, November 2026. Seller prices move often.

Which standards and approvals apply to an RCCB and MCB plant?

Each product has its own Indian Standard, and BIS tests the factory as well as the samples. The numbers below come from the BIS protective device compendium.

Product

Standard

What BIS expects of the factory

MCB

IS/IEC 60898-1:2015

A staffed test lab; tripping and open-contact clearance checks on every piece

RCCB

IS 12640 (Part 1):2024

Tripping, electric strength and test-button checks on every piece; licences moved to the 2024 revision from 25 January 2025

RCBO

IS 12640 (Part 2):2016

Standard Mark compulsory under the 2003 Quality Control Order

The BIS note on RCBOs says all RCBOs sold, made or imported must carry the Standard Mark under a licence. That order's schedule lists RCCBs too. For MCBs, check BIS's compulsory certification list on the day you apply, since the list changes.

What goes into an MCB and an RCCB?

Part

Fitted in

What it does

Check with the supplier

Moulded housing and cover

Both

Holds and insulates everything

Resin specification, cracks, warping

Bimetal strip

MCB

Bends with heat, trips on a lasting overload

Specification, lot identity

Coil and armature

MCB

Trips at once on a short circuit

Coil specification, setting method

Contacts

Both

Carry current, open on trip

Material, joint quality, welding, erosion

Arc chute plates

MCB

Split and cool the arc as contacts open

Shape, material, orientation

Ring core, winding, release, test button

RCCB

Live and neutral pass through the ring; an imbalance opens the contacts; the button simulates a leak

Winding consistency, resistor values

Mechanism, terminals, screws

Both

Toggle, latch, springs, clamping

Binding, contact force, heating

The parts and checks follow a quality guide from the manufacturer VIOX Electric and a published RCCB patent.

How are MCBs and RCCBs made, step by step?

1.       Inspect incoming parts against drawings and log lot numbers, so a later failure traces to a supplier lot.

2.       Build sub-assemblies: bimetal with terminal, coil with armature, contact arm. For an RCCB, wind the secondary on the ring core and fit the release.

3.       Fit the mechanism and contact arms into the base half of the housing.

4.       Add the arc chute and terminals. For an RCCB, add the test resistors and button circuit.

5.       Close the cover and fasten it.

6.       Calibrate the trip points on a fixture, and have the first piece approved before the batch continues.

7.       Test every piece. MCBs get a tripping test and an open-contact clearance check. RCCBs get tripping, electric strength and test-button checks.

8.       Mark, record the lot and pack. BIS's MCB scheme wants a code on each breaker that traces its manufacturing date and batch.

Step 6 decides quality, since a breaker that trips late or early is a safety defect.

Which machines and test equipment does the plant need?

Equipment

Used for

Moulding machine with moulds

Housings and covers

Coil and ring-core winding machines

MCB coils, RCCB secondary

Contact joining set, assembly fixtures

Fixing contacts, building mechanisms

Calibration bench with adjustable current source

Setting thermal and magnetic trip points

Tripping tester, electric strength tester

Routine tests on every piece

Marking machine

Ratings and traceability code

You need not build a short-circuit test plant. BIS's MCB scheme lets a works without one use an independent laboratory, and the RCCB scheme allows subcontracting to a BIS-recognised lab. Short-circuit retests fall every five years.

What does an MCB plant cost, per the NPCS project report?

In the NPCS project report for a miniature circuit breaker plant, capacity is 900 nos per day, plant and machinery is ₹71 lakh and total capital investment is ₹165 lakh. The summary lists a return of 56% and a break-even of 40%; the full report gives the basis for both.

Figure

NPCS report

Working

Capacity

900 nos/day

About 2.7 lakh pieces a year at 300 working days (my assumption)

Plant and machinery

₹71 lakh

71 / 165 = 43% of the total

Total capital investment

₹165 lakh

₹94 lakh (165 minus 71) covers all other project costs

These figures are for MCBs only. An RCCB line adds winding and extra test gear and needs its own estimate. NPCS has prepared project reports since 1994, and its research process is ISO 9001:2015 certified.

What should you do before committing to an RCCB and MCB plant?

•        Start with MCBs only. An MCB line needs no ring-core winding, and one licence gives you test experience before you add RCCBs.

•        Book short-circuit test capacity at a BIS-recognised laboratory before ordering machines.

•        Get written quotes for moulds, winding and calibration equipment, and compare their total with the ₹71 lakh figure above.

An NPCS project report for an MCB plant covers machinery with suppliers, raw material sources, manpower, and the cost, working capital, break-even and cash flow tables banks ask for. It is a base document for supplier and lender talks and does not replace a BIS test report.

Frequently asked questions

Can I run an air conditioner without an MCB?

No. Give the AC its own MCB, sized to its nameplate current. The RCCB upstream only watches for leakage, so without the MCB an overloaded wire or a short circuit has nothing to trip it.

Which is better, RCCB or ELCB?

Choose an RCCB for a new board. Schneider Electric describes the difference as detection method: an RCCB watches residual current, while an ELCB compares live current with earth conductor current. Look for IS 12640 on the label.

Why does my RCCB keep tripping?

Something is leaking current to earth. Damaged wiring, a faulty appliance or moisture are the usual causes, and a surge can also trip it. Switch off the outgoing MCBs, reset the RCCB, then switch circuits on one at a time to find the culprit.

Does an RCCB work without earthing?

It can trip on a leak without an earth wire, because it compares live and neutral currents. Earthing still matters, since it gives fault current a safe path, and an RCCB must never be treated as a substitute for it.

Diksha Garg

Written by

Diksha GargEntrepreneurship Development and Market Research

Diksha Garg works in entrepreneurship development, industrial operations and market research. She holds a BBA from Rukmini Devi Institute of Advanced Studies and studied at IILM from 2019 to 2021. Her experience includes an executive traineeship at HDFC Bank and a financial analyst internship at Bajaj Allianz. She researches the costs, approvals and market data in these business guides, which are reviewed by NPCS founder Ajay Kumar Gupta.

View profile on LinkedIn

How we write and review

Reviewed by Ajay Kumar Gupta, Founder, Niir Project Consultancy Services (NPCS)

Planning a new manufacturing unit?

NIIR prepares detailed project reports and feasibility studies for new projects. Share your requirement and the team will get in touch.