An acyclovir project report is a detailed project report (DPR) for a bulk drug plant that makes acyclovir API from guanine and a side chain built from 1,3-dioxolane. It covers the process, GMP plant and machinery, raw materials, licences, project cost, means of finance, five-year projections, DSCR and break-even that a lender or investor reviews.
Pharma entrepreneurs and existing API makers use it to size the plant and raise a term loan; banks and investors use it to test whether the plant can repay.
Also known as: aciclovir.
Acyclovir manufacturing plant cost in India: the sample economics
The sample report models a 490 kg per day acyclovir plant running 330 days a year, or 1,61,700 kg a year. It starts at 60% capacity, reaches 80% in Year 5 and sells at ₹2,060 per kg before GST.
| Land and site development | 145.71 |
|---|---|
| Building and civil works | 301.99 |
| Plant and machinery | 695.50 |
| Other fixed assets | 92.01 |
| Contingencies | 49.87 |
| Preliminary and pre-operative | 32.13 |
| Working capital margin | 76.89 |
| Total | 1,394.10 |
| Promoter's contribution (25%) | 348.52 |
|---|---|
| Term loan from bank (75%) | 1,045.58 |
| Cash credit limit (separate) | 230.66 |
| Total project cost | 1,394.10 |
Term loan at 10.5% with a 6-month moratorium and 54 monthly instalments. DSCR is lowest at 1.34 in Year 2, the first year of full instalments. All figures are illustrative.
Acyclovir manufacturing process, step by step
The sample plant uses the acetyl route. Guanine is protected, joined to a side chain made from 1,3-dioxolane, then freed and purified until it meets the pharmacopoeia.
- Acetylation of guanine
Guanine is refluxed with acetic anhydride and acetic acid, with a little phosphoric acid, to give diacetylguanine. Guanine itself barely dissolves, so this step makes the next reaction possible.
- Side-chain preparation
1,3-Dioxolane is opened with acetic anhydride over p-toluenesulfonic acid, and the diacetate is distilled before use.
- Condensation
Diacetylguanine reacts with about two equivalents of the side chain in toluene at about 110–120 °C over an acid catalyst. Too much side chain polymerises and lowers yield.
- Deacetylation
Aqueous methylamine or ammonia removes the acetyl groups and gives crude acyclovir.
- Purification
The crude product is treated with activated carbon and recrystallised from water. This removes colour and most of the unwanted N7 isomer.
- Drying, milling and release
Wet cake is centrifuged, dried, milled and sifted to the buyer's particle size. Each batch is released only after HPLC assay and related-substances tests.
Which acyclovir process route should a new plant choose?
Two chemical routes dominate the patent literature. Both attach the same side chain to guanine; they differ in how guanine is protected and how well they steer the reaction to the right nitrogen.
| Acetyl route | Guanine, acetic anhydride and 1,3-dioxolane with an acid catalyst. Raw materials are widely traded and patent examples report yields of about 70%. Used in our sample report. |
|---|---|
| Silyl route | Guanine is silylated with hexamethyldisilazane, then alkylated with 1,3-dioxolane over a triflate catalyst. It gives better N9 selectivity but needs dry handling and costlier reagents. |
| The N7 isomer | The main impurity in both routes. It is hard to separate, so the route and reaction temperature are chosen to favour N9, and recrystallisation removes the rest. |
| Make or buy diacetylguanine | Buying the intermediate saves one reactor train but raises raw material cost and ties you to one supplier. |
| Room for valacyclovir | Valacyclovir is made by esterifying acyclovir with protected L-valine. Space for a second train lets you add it later. |
Raw materials for acyclovir and their share of cost
Guanine is 52% of raw material spend in the sample, and raw materials are 53.2% of sales. Guanine price and condensation yield together decide most of your cost per kg.
| Raw material | Share of cost | Year 3 (₹ lakh) |
|---|---|---|
| Guanine | 52% | 645.18 |
| Acetic anhydride and acetic acid | 16% | 198.52 |
| 1,3-Dioxolane | 14% | 173.70 |
| Toluene, methanol and other solvents | 8% | 99.26 |
| Aqueous methylamine or ammonia | 6% | 74.44 |
| Activated carbon and catalysts | 4% | 49.63 |
| Total | 100% | 1,240.73 |
The solvent line assumes most toluene and methanol is recovered and reused. Without recovery it rises sharply.
Plant and machinery for an acyclovir API plant
Reactors are the largest item. GMP equipment, meaning purified water, HVAC and the QC laboratory, adds up to about 22% of the machinery cost.
| Equipment | What it does | Sample cost (₹ lakh) |
|---|---|---|
| Glass-lined and stainless steel reactors | Acetylation, condensation and deacetylation | 208.65 |
| Centrifuges and nutsche filters | Separate crystals from mother liquor | 83.46 |
| Crystallisers and receivers | Recrystallise and hold batches | 55.64 |
| Vacuum tray and fluid bed dryers | Dry the wet cake | 69.55 |
| Solvent recovery and distillation | Recover toluene and methanol | 90.42 |
| Multi-mill, sifter and blender | Size and blend the final API | 34.77 |
| Purified water system and HVAC | Water for recrystallisation, clean air for the final stage | 69.55 |
| QC laboratory with HPLC | Test raw materials and release batches | 83.46 |
| Total plant and machinery | 695.50 | |
Costs are the sample report's estimates. Get current quotations before you finalise.
Utilities and manpower for a 490 kg per day plant
| Power and fuel | ₹126.26 lakh in Year 3 of the sample, about 5.4% of sales. Reflux, distillation and drying draw most of the steam and power. |
|---|---|
| Cooling | Chilled water or brine for crystallisation and solvent condensers. Short cooling capacity slows every batch. |
| Water | Purified water for recrystallisation and final washing, plus process and cleaning water that goes to the effluent plant. |
| Manpower | 58 people in the sample: 9 in management and supervision, 20 skilled operators and 29 semi-skilled workers. Year 1 cost is ₹131.28 lakh. |
| Technical staff | The drug licence application names competent staff for manufacturing, quality control and quality assurance, with their qualifications and experience. |
Licences and approvals for an acyclovir bulk drug plant
Acyclovir is a drug, so the plant needs drug and GMP approvals on top of the usual factory consents. Start these early, because inspection follows construction.
| Drug manufacturing licence | From the State Drugs Control authority under the Drugs and Cosmetics Rules, 1945, applied for online in the Form 24 series. |
|---|---|
| GMP | Revised Schedule M applies. The extended deadline for smaller makers, with turnover up to ₹250 crore, ended on 31 December 2025. A new plant must comply from the start. |
| Environmental clearance | Bulk drugs and intermediates fall under activity 5(f), synthetic organic chemicals, of the EIA Notification 2006. Prior clearance is needed before construction. |
| Pollution board consent | Pharmaceuticals are Red category. You need consent to establish and operate from the State Pollution Control Board, with effluent treatment and solvent handling in place. |
| Buyer documents | A drug master file, stability data and audit readiness for each formulation customer. Regulated export markets add their own inspections. |
Checked October 2026. Rules and forms vary by state; confirm with your State Drugs Control office and pollution board.
Who buys acyclovir API in India?
Acyclovir treats herpes, cold sores, chickenpox and shingles. It is sold as tablets, creams, eye ointments and, as acyclovir sodium, injections. Valacyclovir makers also buy it as their starting material.
Buyers approve a new API source only after an audit, validation batches and stability data. Most new plants start with domestic formulators and traders, then move to export once their file is accepted.
- Tablet and cream formulation companies
- Injectable and eye ointment makers
- Valacyclovir manufacturers
- Contract manufacturers supplying exporters
- Bulk drug traders and exporters
Plan for price competition: acyclovir is on the Department of Pharmaceuticals' PLI list for bulk drugs, with one approved plant listed at 525 MT of capacity (as on 30 December 2022). That is more than three times our sample plant's 161.7 MT a year, so your report must show a cost per kg that holds up.
Mistakes that weaken an acyclovir project report
- Taking patent yields as plant yields
Patent examples report about 70% from diacetylguanine. Early commercial batches usually run lower, so output should ramp up rather than start at the best figure.
- No budget for rework
Batches that fail on the N7 isomer or related substances go back for recrystallisation. That costs solvent, time and capacity the projections must allow for.
- Leaving out solvent recovery
Buying fresh toluene and methanol for every batch raises cost and effluent load. The recovery plant belongs in both the machinery list and the running cost.
- Pricing GMP as an afterthought
Purified water, HVAC and the QC laboratory are about 22% of sample machinery cost. Revised Schedule M makes them part of the plant, not an extra.
- Assuming buyers pay fast
Trade receivables are the largest working capital item in the sample, at 45 days. Slow approvals and longer credit both raise the cash credit you need.
How NPCS helps you plan an acyclovir plant
- Capacity and routeSize the plant and compare the acetyl and silyl routes for your budget and buyers.
- Equipment and GMP layoutReactor trains, solvent recovery and a Schedule M layout with current quotations.
- Bank-ready project reportProjections, DSCR and working capital in the format your lender appraises.
- Approvals roadmapDrug licence, environmental clearance and pollution consent in the right order for your state.
NPCS's client list records 269 project assignments in specialty chemicals, prepared since 1994 for entrepreneurs, companies and banks in India and abroad.
What's inside the acyclovir sample report
- Introduction
- Uses and applications
- Market potential
- Manufacturing process
- Raw materials
- Plant and machinery
- Land, building and utilities
- Manpower
- Licences and approvals
- Project cost and means of finance
- Working capital
- Projected profitability
- Cash flow statement
- Projected balance sheet
- Depreciation
- Term loan repayment
- Debt service coverage
- Break-even analysis
- Financial ratios
- Key assumptions
- Conclusion
- Monthly loan repayment schedule
18 pages, five-year projections, illustrative figures.
Open sample reportFree sample or a report for your project?
| What you get | Free sample | NPCS report for your project |
|---|---|---|
| Capacity and location | Typical unit | Your capacity, site and state |
| Figures | Illustrative | Built on current prices and quotations |
| Machinery suppliers and quotations | No | Yes |
| Market survey for your region | No | Yes |
| Bank or scheme format (PMEGP, term loan) | No | Yes |
| Use for a loan application | No | Yes |
Find NPCS project reports in your budget
What clients say about NPCS
4.7
264 Google reviews, as of 20 Oct 2026
Clients most often mention
- feasibility reports 18
- project report 16
- helpful for startups 15
- detailed reports 8
-
Excellent experience with Niir Project Consultancy Services. Their Techno-Economic Feasibility Reports are incredibly detailed and backed by solid market data.
Piyush Singh, Google review, 2026
-
Niir Project Consultancy Services offers excellent guidance for business setup. Their market survey and feasibility reports saved us a lot of time and helped us make informed decisions. Highly recommended
Saroj Yadav, Google review, 2026 View on Google
-
In an era of information overload, NIIR stands out for its precision. Their technical consultancy and market feasibility studies are world-class.
Shrishti Gautam, Google review, 2026
-
NIIR Project Consultancy Services provides useful books and reports for students, entrepreneurs, and small businesses. Their content is easy to understand and focuses on practical ideas for starting and managing industries. Overall, NIIR is helpful for learning about business and project planning.
Raj Yadav, Google review, 2026
Acyclovir project report: frequently asked questions
How much does it cost to set up an acyclovir manufacturing plant in India?
A GMP plant making 300–600 kg of acyclovir a day needs roughly ₹10–20 crore, including land, building, utilities, a QC laboratory and working capital margin. Our sample report models a 490 kg per day plant at ₹1,394 lakh, with ₹696 lakh in plant and machinery. These ranges are indicative; your report costs the plant for your capacity, site and process route.
What raw materials are used to make acyclovir?
Guanine is the main raw material, joined to a side chain made from 1,3-dioxolane and acetic anhydride. Toluene and methanol serve as solvents, aqueous methylamine or ammonia removes the protecting groups, and activated carbon cleans the product. In our sample report guanine alone is 52% of raw material cost, so its price moves profit more than any other input.
How is acyclovir manufactured?
Guanine is first acetylated to diacetylguanine. It is then condensed with a dioxolane diacetate side chain in toluene at about 110–120 °C over an acid catalyst. The acetyl groups are removed with aqueous methylamine or ammonia, and the crude product is carbon treated, recrystallised from water, dried, milled and tested by HPLC before release.
Which licences are needed to manufacture acyclovir API?
You need a drug manufacturing licence from the State Drugs Control authority under the Drugs and Cosmetics Rules, 1945, with GMP to revised Schedule M. Bulk drugs also need prior environmental clearance under the EIA Notification 2006, and pharmaceutical units are Red category for pollution board consent. Udyam, GST, factory and fire approvals apply as for any plant.
Is acyclovir API manufacturing profitable?
In our illustrative sample, a 490 kg per day plant earns a 16% return on investment in Year 3. It breaks even at about 42% of capacity and pays back in about 4.2 years. Real results depend on guanine prices, condensation yield, solvent recovery and how fast formulation buyers approve you as a supplier. The report should test each of these.
Is the sample report free and can I use it for a loan?
The sample is free to view and download. It is an illustrative report that shows the format and depth of an NPCS report. Its figures are representative and not based on a real project, so it should not be submitted to a bank. For a loan, NPCS prepares a report for your own capacity, location and process route.
Can I get an acyclovir project report PDF for a bank loan?
Yes. The sample PDF on this page shows the 21 chapters and loan annexure a bank reviews. For an actual loan, NPCS prepares a report on your own plant, with machinery quotations, raw material prices, GMP costs and projections. Lenders usually check DSCR, promoter contribution, working capital and the approval plan before they appraise a bulk drug project.
Sources and references
- Update on PLI for Bulk Drugs (as on 30.12.2022)Department of Pharmaceuticals, Ministry of Chemicals and Fertilizers, checked Oct 2026
- Extension of timeline for implementation of revised Schedule M (circular, 6 Feb 2025)Pharmaceuticals Export Promotion Council of India, checked Oct 2026
- Licence for manufacturing pharmaceutical products: checklistDirectorate of Food and Drugs Administration, Government of Goa, checked Oct 2026
- Standard terms of reference for EIA studies: activity 5(f), synthetic organic chemicals industryMinistry of Environment, Forest and Climate Change, checked Oct 2026
- Categorisation of industrial sectors under Red as per CPCB criteriaState Pollution Control Board, Odisha, checked Oct 2026
- US Patent 5,567,816: Preparation of acyclovir using 1,3-dioxolaneUnited States Patent and Trademark Office, checked Oct 2026