What is a sorbitol project report?
A sorbitol plant project report is a detailed project report (DPR) for a unit that hydrogenates dextrose over a nickel catalyst to make sorbitol, usually sold as a 70% solution. It sets out the process, hydrogen supply, machinery, raw materials, market, project cost, means of finance, five-year projections, DSCR and break-even that a bank needs.
Promoters use it to size the plant and raise a term loan; lenders and investors use it to check whether the margin between dextrose and sorbitol can repay the debt.
Also known as: sorbitol project report, plant sorbitol project report, sorbitol manufacturing business plan, DPR for sorbitol 70% solution plant.
Sorbitol manufacturing plant cost in India and plant economics
Our sample report models a plant making 19 MT per day of sorbitol 70% solution, or 6,270 MT a year, running 330 days. It starts at 60% capacity and reaches 80% in Year 5, selling at ₹46,700 per MT before GST.
| Land and site development | 100.63 |
|---|---|
| Building and civil works | 265.84 |
| Plant and machinery | 509.27 |
| Other fixed assets | 78.89 |
| Contingencies | 38.76 |
| Preliminary and pre-operative | 24.83 |
| Working capital margin | 68.80 |
| Total | 1,087.02 |
| Promoter's contribution (25%) | 271.76 |
|---|---|
| Term loan from bank (75%) | 815.26 |
| Cash credit limit (separate) | 206.41 |
| Total project cost | 1,087.02 |
Term loan at 10.5% with a 6-month moratorium and 54 monthly instalments. Minimum DSCR is 1.34. All figures are illustrative.
Sorbitol manufacturing process
Sorbitol is glucose with its aldehyde group reduced to an alcohol by hydrogen. A standalone plant buys dextrose and runs six stages; most of the engineering sits in the reactor and in removing nickel afterwards.
- Feed preparation
Dextrose is dissolved in demineralised water to about 50% solids and the pH is adjusted, because chlorides and a wrong pH poison the catalyst.
- Hydrogenation
The solution reacts with hydrogen over Raney nickel in a pressure reactor at about 120–150 °C until reducing sugars fall to a trace.
- Catalyst separation
The nickel catalyst settles and is filtered out of the crude liquor; most of it goes back into the next batch with a small fresh top-up.
- Purification
Activated carbon removes colour, then cation and anion exchange columns strip dissolved nickel and other ions.
- Evaporation
A multiple effect evaporator concentrates the liquor to about 70% sorbitol, the grade most buyers take.
- Testing and packing
Each batch is checked for assay, reducing sugars and nickel, then filled into drums, IBC totes or road tankers.
Technology choices that decide a sorbitol plant's cost
Three choices fix most of the capital cost and the margin. The sample report takes the lighter option in each row; the alternatives are common in larger plants.
| Feedstock | Bought-in dextrose keeps the plant small but leaves you paying a starch maker's margin. An own maize starch and glucose line costs far more but controls the main input. |
|---|---|
| Hydrogen source | A water electrolyser is simple and clean but uses a lot of power. Large plants often crack methanol or take hydrogen from a nearby gas supplier. |
| Reactor mode | Batch autoclaves with slurry catalyst suit 10–30 MT per day. Continuous fixed-bed reactors suit bigger plants with steady feed. |
| Product form | 70% solution needs only an evaporator. Crystalline powder adds crystallisers, centrifuges, a fluid bed dryer and a mill, and sells at a higher price. |
| Grade | Technical and food grades are easier to sell in bulk. Pharmacopoeia grades fetch more but need tighter nickel removal, documentation and buyer audits. |
Raw materials for sorbitol production
One MT of 70% solution holds 0.7 MT of sorbitol, which needs about 0.69 MT of glucose solids and under 8 kg of hydrogen. Dextrose is 90% of raw material cost in our sample, so contracts with two or more starch makers matter more than any other purchase.
| Raw material | Share of cost | Year 3 (₹ lakh) |
|---|---|---|
| Dextrose or refined glucose syrup | 90% | 1,046.95 |
| Raney nickel catalyst | 4% | 46.53 |
| Activated carbon | 3% | 34.90 |
| Ion exchange regeneration chemicals | 3% | 34.90 |
| Total | 100% | 1,163.28 |
Raw materials are 56.8% of sales in the sample. Hydrogen is made on site, so its cost sits under power.
Machinery for a sorbitol plant
The hydrogenation reactor system is the largest single item in our sample, followed closely by the hydrogen plant. Together they are close to half of the machinery cost.
| Machine | What it does | Sample cost (₹ lakh) |
|---|---|---|
| Hydrogenation reactor system | Reacts glucose with hydrogen under pressure | 127.32 |
| Water electrolyser hydrogen plant | Makes, compresses and stores hydrogen | 112.04 |
| Multiple effect evaporator | Concentrates liquor to 70% | 71.30 |
| Carbon and ion exchange columns | Remove colour and dissolved nickel | 50.93 |
| Feed preparation system | Dissolves dextrose to reactor feed | 40.74 |
| Catalyst filtration and recovery | Separates nickel for reuse | 40.74 |
| Steam boiler and cooling tower | Heat for reaction and evaporation | 40.74 |
| Storage tanks and drum filling | Holds and packs finished solution | 25.46 |
| Total plant and machinery | 509.27 | |
Costs are the sample report's estimates for a 19 MT per day plant. Reactors and hydrogen equipment need pressure-rated design, so get current quotations before you finalise.
Hydrogen, power and steam for a sorbitol plant
Utilities are where sorbitol differs most from other sweeteners. Power and fuel are 7.5% of sales in our sample, but the real figure depends on how you make hydrogen.
| Hydrogen | About 7.7 kg (86 Nm³) per MT of 70% solution by stoichiometry, plus losses. At 19 MT per day that is roughly 1,650 Nm³ a day. |
|---|---|
| Power | An alkaline electrolyser needs roughly 4.5–5.5 kWh per Nm³ of hydrogen (indicative), so electrolysis alone can take 400–475 kWh per MT of solution. |
| Steam | For the reactor and, above all, the evaporator. More evaporator effects or vapour recompression cut steam per MT. |
| Water | Demineralised water for feed make-up and ion exchange rinsing; the ion exchange plant also produces regeneration effluent to treat. |
| Nitrogen and safety | Nitrogen purging, gas detectors and flameproof electricals around the hydrogen area. |
Hydrogen figures are calculated from the reaction; power figures are indicative and vary with electrolyser make.
Licences and approvals for a sorbitol plant
| Pollution board consent | Consent to establish and operate from the State Pollution Control Board, with authorisation for spent nickel catalyst as hazardous waste |
|---|---|
| Hydrogen safety | PESO clearance for storing and handling compressed hydrogen; hydrogen is also listed as a hazardous chemical under the MSIHC Rules, 1989. PESO's hydrogen-specific rules are still in draft as of October 2026 |
| FSSAI licence | Needed to sell food grade sorbitol. Food units above 2 MT per day fall under the central licence list in Schedule 1 of the FSSAI licensing regulations |
| Product standard | IS 4750 covers food grade sorbitol powder, with nickel capped at 2 mg/kg in the April 2024 draft revision. Pharma buyers test against pharmacopoeia monographs |
| GST and HSN | Sorbitol (D-glucitol) is HSN 2905 44. Organic chemicals of chapter 29 are taxed at 18% under the September 2025 rate schedule |
| Plant approvals | Udyam, factory licence, fire NOC and registration of the steam boiler with the state boiler inspectorate |
Market for sorbitol in India
Toothpaste is the anchor market: sorbitol is the main humectant that stops paste from drying out, and oral care makers buy it in tanker loads all year. Vitamin C producers use it as their starting material, and pharmaceutical syrup and sugar-free food makers buy smaller lots at better prices.
- Toothpaste and oral care manufacturers
- Pharmaceutical syrup and formulation makers
- Vitamin C producers
- Confectionery, chewing gum and food processors
- Cosmetic and personal care makers
- Chemical traders and exporters
Where a standalone plant wins: the big Indian producers are integrated with maize starch, so a new plant cannot beat them on feedstock cost. It wins on location near buyers, consistent low-nickel quality and reliable supply to regional toothpaste and syrup makers.
Mistakes that weaken a sorbitol plant project report
- Testing only the sorbitol price
Profit sits in the gap between dextrose and sorbitol prices. A report must show what happens when dextrose rises and sorbitol does not.
- Costing hydrogen as a share of sales
Electrolytic hydrogen is a large power load. It needs its own line in the cost sheet, based on kWh per Nm³ and your power tariff.
- Pricing all output at pharma grade
Pharma buyers take months to approve a new supplier. Early sales are mostly technical and food grade at lower prices.
- No allowance for catalyst loss
Some nickel is lost each batch and spent catalyst must go to an authorised recycler. Both are running costs.
- Under-sizing working capital
Receivables are the largest current asset in our sample at 45 days of sales, with another 30 days of dextrose in stock.
How NPCS helps you set up a sorbitol plant
- Feedstock and capacityCompare bought-in dextrose with your own starch line, and size the plant to your buyers.
- Hydrogen and process routeWeigh electrolysis against other hydrogen sources, and batch against continuous reactors.
- Bank-ready project reportProjections, DSCR, sensitivity to dextrose price and working capital in your lender's format.
- Approvals and layoutHydrogen area layout, boiler, pollution consent and FSSAI steps for your state.
NPCS's client list includes 3 assignments on sorbitol among 23 in sweeteners, and NPCS has prepared project reports for sweetener, glucose and starch-based units since 1994.
What's inside the sorbitol sample report
- Introduction
- Uses and applications
- Market potential
- Manufacturing process
- Raw materials
- Plant and machinery
- Land, building and utilities
- Manpower
- Licences and approvals
- Project cost and means of finance
- Working capital
- Projected profitability
- Cash flow statement
- Projected balance sheet
- Depreciation
- Term loan repayment
- Debt service coverage
- Break-even analysis
- Financial ratios
- Key assumptions
- Conclusion
- Monthly loan repayment schedule
18 pages, five-year projections, illustrative figures.
Open sample reportFree sample or a report for your project?
| What you get | Free sample | NPCS report for your project |
|---|---|---|
| Capacity and location | Typical unit | Your capacity, site and state |
| Figures | Illustrative | Built on current prices and quotations |
| Machinery suppliers and quotations | No | Yes |
| Market survey for your region | No | Yes |
| Bank or scheme format (PMEGP, term loan) | No | Yes |
| Use for a loan application | No | Yes |
Real NPCS sorbitol project reports
These are sorbitol project reports NPCS has prepared, with the plant capacity, total capital investment, rate of return and break-even worked out in each. Costs have moved since some were written, so we bring any of them up to date for your capacity and location.
| Project report | Plant capacity | Total investment | Rate of return | Break-even | Action |
|---|---|---|---|---|---|
| Sorbitol | 40.0 Tonnes/Day | ₹1 lakh | 1% | 1% | Get this report |
| Sorbitol | 4500 MT/Annum | ₹1.86 crore | 43% | 69% | Get this report |
| Sorbitol | Sorbitol:3,000 MT Per Annum | ₹5.75 crore | 27% | 55% | Get this report |
| Vitamin ‘C’ from Sorbitol | 600 kg/day | ₹7.17 crore | 24% | 50% | Get this report |
| Sorbitol | 6 MT Per Day | ₹7.9 crore | 28% | 47% | Get this report |
| Sorbitol | 47 MT/Day | ₹12.35 crore | 26% | 41% | Get this report |
Figures as worked out in each NPCS report. Total investment includes plant and machinery, land and building, and working capital.
What clients say about NPCS
4.7
264 Google reviews, as of 20 Oct 2026
Clients most often mention
- feasibility reports 18
- project report 16
- helpful for startups 15
- detailed reports 8
-
Excellent experience with Niir Project Consultancy Services. Their Techno-Economic Feasibility Reports are incredibly detailed and backed by solid market data.
Piyush Singh, Google review, 2026
-
Niir Project Consultancy Services offers excellent guidance for business setup. Their market survey and feasibility reports saved us a lot of time and helped us make informed decisions. Highly recommended
Saroj Yadav, Google review, 2026 View on Google
-
In an era of information overload, NIIR stands out for its precision. Their technical consultancy and market feasibility studies are world-class.
Shrishti Gautam, Google review, 2026
-
NIIR Project Consultancy Services provides useful books and reports for students, entrepreneurs, and small businesses. Their content is easy to understand and focuses on practical ideas for starting and managing industries. Overall, NIIR is helpful for learning about business and project planning.
Raj Yadav, Google review, 2026
Sorbitol project report: frequently asked questions
How much does it cost to set up a sorbitol plant in India?
A standalone plant making 15–25 MT per day of 70% solution from bought-in dextrose needs roughly ₹10–20 crore. Plants of 50 MT per day or more cost several times that, and units built with their own maize starch line run well above ₹100 crore. These ranges are indicative. Our sample report models a 19 MT per day plant at ₹1,087 lakh.
What raw material is used to make sorbitol?
Sorbitol is made from dextrose, either crystalline dextrose monohydrate or a refined glucose syrup of high purity, which most producers make from maize starch. Hydrogen, a nickel catalyst, activated carbon and ion exchange chemicals are the other inputs. In our sample report dextrose is 90% of raw material cost, so its price decides the plant's margin.
How is sorbitol manufactured?
Dextrose is dissolved in demineralised water and reacted with hydrogen over a Raney nickel catalyst in a pressure reactor at about 120–150 °C. The catalyst is filtered out and reused, carbon and ion exchange columns remove colour and dissolved nickel, and an evaporator concentrates the liquor to a 70% solution. Powder grades need extra crystallising and drying.
Is a sorbitol manufacturing business profitable?
It can be, but the margin is thin for a plant that buys its dextrose. In our illustrative sample, a 19 MT per day plant earns a 16% return on investment in Year 3. It breaks even at about 42% of capacity and pays back in about 4.2 years. The gap between dextrose and sorbitol prices moves profit more than any other figure.
What licences are needed for a sorbitol plant?
Beyond Udyam, GST, factory licence and fire NOC, a sorbitol plant needs State Pollution Control Board consent and boiler registration. It also needs an FSSAI licence to sell food grade sorbitol, and clearance for storing and handling hydrogen. Pharmaceutical buyers also check the product against pharmacopoeia specifications and audit the plant before approving it as a supplier.
What is the difference between sorbitol 70% solution and sorbitol powder?
Sorbitol 70% solution is the liquid straight from the evaporator and is what toothpaste and vitamin C makers buy in drums or tankers. Powder is crystallised, dried and milled, and is used in tablets, chewing gum and dry foods. A powder line adds crystallisers, centrifuges and dryers, so most new plants start with the solution and add powder later.
Is the sample report free and can I use it for a loan?
The sample is free to view and download. It is an illustrative report that shows the format and depth of an NPCS report. Its figures are representative and not based on a real project, so it should not be submitted to a bank. For a loan, NPCS prepares a report for your own capacity, location and feedstock.
Sources and references
- Notification No. 9/2025-Integrated Tax (Rate), GST rate schedulesCentral Board of Indirect Taxes and Customs, checked Oct 2026
- Draft IS 4750 (second revision): Sorbitol powder, food grade, specificationBureau of Indian Standards, checked Oct 2026
- Food Safety and Standards (Licensing and Registration of Food Businesses) Regulations, 2011Food Safety and Standards Authority of India, checked Oct 2026
- Hydrogen ecosystem and the role of PESOPetroleum and Explosives Safety Organisation, via PNGRB, checked Oct 2026